Project Duration
Stipulated Date of Commencement
October 05 2022
Stipulated Date of Completion /
Likely Date of Completion March 31 2024
Likely Date of Completion March 31 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,609,407.10
Awarded for
₹ 25,963,270.00
Project highlights
Roofing work at Community Health Centre, Valpoi
Contractors
M/s A. R. Constructions
Consultants
Inhouse