Project Duration
Stipulated Date of Commencement October 17 2021
Stipulated Date of Completion /
Likely Date of Completion
January 16 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,241,960.89
Awarded for ₹ 25,063,416.99

Project highlights

Demolition & Re-construction work.
Ground floor – Bank, Panchayat office, Health.
First floor – Multipurpose Hall.

 
Gallery Image
Contractors
M/s. V. Construct
Gallery Image
Consultants
M/S. Gurudutt Sanzgiri
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme 2013 – Reconstruction of Panchayat building at V.P.Honda.

View Project
Similar Project

CCTV & other works.

View Project
Similar Project

Beautification works in Sanguem Town

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.