Project Duration
Stipulated Date of Commencement October 17 2021
Stipulated Date of Completion /
Likely Date of Completion
January 16 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,241,960.89
Awarded for ₹ 25,063,416.99

Project highlights

Demolition & Re-construction work.
Ground floor – Bank, Panchayat office, Health.
First floor – Multipurpose Hall.

 
Gallery Image
Contractors
M/s. V. Construct
Gallery Image
Consultants
M/S. Gurudutt Sanzgiri
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Construction of Panchayat Ghar along with Community Hall at V.P. Uguem in Sanguem Taluka.

View Project
Similar Project

Construction of Washrooms at Old Goa for Exposition 2014 – Package II – Near Se Cathedral Church and St. Cajetan Church.

View Project
Similar Project

Civil, Plumbing & Electrical works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.