Project Duration
Stipulated Date of Commencement
February 13 2019
Stipulated Date of Completion /
Likely Date of Completion February 29 2024
Likely Date of Completion February 29 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,162,590.00
Awarded for
₹ 5,132,517.00
Project highlights
The scope of work includes landscaping work of premises.
Contractors
M/s. Sri Sri Akruthi Projects Pvt. Ltd.
Consultants
M/s. M:OFA Studios Pvt. Ltd.