Project Duration
Stipulated Date of Commencement
March 02 2024
Stipulated Date of Completion /
Likely Date of Completion September 01 2025
Likely Date of Completion September 01 2025
Status
10%
Completed
Cost (₹)
Estimated at
₹ 152,383,300.00
Awarded for
₹ 143,889,955.21
Project highlights
The project includes 28 nos. of classrooms & spacious laboratories. Also, consists of large multipurpose hall.
Contractors
M/s. R.Z. Malpani
Consultants
M/s. Datta Kare Associates