Project Duration
Stipulated Date of Commencement March 02 2024
Stipulated Date of Completion /
Likely Date of Completion
September 01 2025
Status
10%
Completed
Cost (₹)
Estimated at ₹ 152,383,300.00
Awarded for ₹ 143,889,955.21

Project highlights

The project includes 28 nos. of classrooms & spacious laboratories. Also, consists of large multipurpose hall.

 
Gallery Image
Contractors
M/s. R.Z. Malpani
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Development work of Integrated Education complex at Cujira, Bambolim, Tiswadi, Goa

View Project
Similar Project

Construction Of Multipurpose Hall Having Badminton Court, Gymnasium, Changing Room and Other Facilities at Socorro Ground. – Mechanical, Electrical, Plumbing scope of work pertaining to Lap Pool, Diving Pool and Baby Pool.

View Project
Similar Project

Demolition & Construction of Margao Government ITI & Govt. Multipurpose Higher Secondary School at Borda – Phase I – Interior Works (2nd Call)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.