Project Duration
Stipulated Date of Commencement
January 21 2024
Stipulated Date of Completion /
Likely Date of Completion July 20 2024
Likely Date of Completion July 20 2024
Status
0%
Completed
Cost (₹)
Estimated at
₹ 28,560,552.00
Awarded for
₹ 25,144,030.82
Project highlights
Renovation of the Office premises of Commissioner, Labour and Employment, with new layout, furniture, Electrical & HVAC works.
Contractors
M/s. Aai Jee Interiors
Consultants
M/s Amit Sukthankar
See Similar Projects
Repairs/ Maintenance of Buildings under Directorate of Food and Drugs Administration, Bambolim – Goa. S.H. –Maintenance Contract for the 180kVA Diesel Generator set installed at Directorate of Food and Drugs Administration, Bambolim for three years (2021-2024)
View Project
Construction of Multipurpose Community Hall for Department of Tribal Welfare at Nirankal in Ponda Taluka
View Project
Protection & Restoration of Mandovi River Coastline from Miramar Circle to Youth Hostel and from Kala Academy to ESG
View Project