Project Duration
Stipulated Date of Commencement
August 07 2023
Stipulated Date of Completion /
Likely Date of Completion February 29 2024
Likely Date of Completion February 29 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 5,316,768.75
Awarded for
₹ 4,998,950.00
Project highlights
The scope of work includes supply, Installation, Testing and Commissioning of Moduler Operation Theatre
Contractors
M/s Mediconz International
Consultants
M/s. Saolapurkar and Associates