Project Duration
Stipulated Date of Commencement
May 31 2023
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
85%
Completed
Cost (₹)
Estimated at
₹ 27,073,347.00
Awarded for
₹ 23,436,764.00
Project highlights
Providing 100 KLD STP for Hospital Premises along with allied Civil works.
Contractors
M/s. Concept Creator
Consultants
M/s. Saolapurkar and Associates
See Similar Projects
Balance electrical and LV works
View Project
Expansion and Upgradation of the infrastructure of Primary Health Centre, Sanguem
View Project
Upgradation of existing Rural Medical Centre at Collem, Dharbandora – Civil, Plumbing, Electrical, Lift, HVAC and Fire Fighting works
View Project





