Project Duration
Stipulated Date of Commencement
March 05 2024
Stipulated Date of Completion /
Likely Date of Completion December 04 2024
Likely Date of Completion December 04 2024
Status
25%
Completed
Cost (₹)
Estimated at
₹ 17,043,187.00
Awarded for
₹ 16,781,944.68
Project highlights
Construction of Community hall for Tribal community for conducting social and cultural activities.
Contractors
M/s. Sri Srinath Infra
Consultants
Ms Murty & Manyam
See Similar Projects
Construction of Sewage Treatment Plant including Sewage Network at Institute of Psychiatry & Human Behaviour, Bambolim, Goa -Electro-mechanical work
View Project
Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College. S.H.: Maintenance of ductable VRV air conditioners in Lecture Hall 4, 5 & 6 at Goa Medical College for a period of five years (2019-2024)
View Project
Additional Miscellaneous Work in New High Court Complex at Penha De Franca, Porvorim – Goa.
View Project