Project Duration
Stipulated Date of Commencement March 12 2023
Stipulated Date of Completion /
Likely Date of Completion
July 31 2024
Status
95%
Completed
Cost (₹)
Estimated at ₹ 54,632,130.14
Awarded for ₹ 49,269,330.17

Project highlights

Setting up 11 KV Substation for IPHB Campus at Bambolim.

 
Gallery Image
Contractors
M/s. Imperial Engineering Company
Gallery Image
Consultants
M/s. FP Project Management
 
Similar Projects

See Similar Projects

Similar Project

Balance Fire-fighting works

View Project
Similar Project

Supply, Installation, Testing and Commissioning of 100KLD Sewage Treatment Plant and allied Civil works.

View Project
Similar Project

Upgradation of existing Rural Medical Centre at Collem, Dharbandora – Civil, Plumbing, Electrical, Lift, HVAC and Fire Fighting works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.