Project Duration
Stipulated Date of Commencement
December 05 2023
Stipulated Date of Completion /
Likely Date of Completion August 04 2024
Likely Date of Completion August 04 2024
Status
80%
Completed
Cost (₹)
Estimated at
₹ 23,722,708.30
Awarded for
₹ 18,006,988.09
Project highlights
Furniture works.
Contractors
M/s. Nilkamal Limited
Consultants
M/s. FP Project Management