Project Duration
Stipulated Date of Commencement
February 26 2024
Stipulated Date of Completion /
Likely Date of Completion August 25 2025
Likely Date of Completion August 25 2025
Status
8%
Completed
Cost (₹)
Estimated at
₹ 176,481,420.00
Awarded for
₹ 164,727,928.63
Project highlights
Construction of Hospital building, comprising of Ground + 1st floor with OPD facilities, Male & Female wards, Casualty, Laboratory, X-ray Machine Room, etc.
Contractors
M/s. R.Z. Malpani
Consultants
M/s. KICONS Limited