Project Duration
Stipulated Date of Commencement
June 24 2024
Stipulated Date of Completion /
Likely Date of Completion December 23 2025
Likely Date of Completion December 23 2025
Status
0%
Completed
Cost (₹)
Estimated at
₹ 172,099,541.50
Awarded for
₹ 162,492,049.56
Contractors
M/s. V.R. & Company
Consultants
M/s. KICONS Limited