Project Duration
Stipulated Date of Commencement February 17 2024
Stipulated Date of Completion /
Likely Date of Completion
February 16 2025
Status
2%
Completed
Cost (₹)
Estimated at ₹ 20,957,778.77
Awarded for ₹ 22,641,244.50

Project highlights

The project is GH structure with Diagnotics and Out Patient Department, Casualty Room; 1 & 2 Treatment Room, Laboratory, Pharmcay, Immunization room and Sanitory accommodation.

 
Gallery Image
Contractors
M/s A. Y. Gulumkar
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Balance electrical and LV works

View Project
Similar Project

Construction of Hospital at Bicholim for Deendayal Janaseva Pratisthan Trust under CSR Funds of Indian Oil Corporation Ltd.

View Project
Similar Project

Construction of IInd phase of Goa Dental College and Hospital at Bambolim, Goa – Fire escape ramp.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.