Project Duration
Stipulated Date of Commencement February 18 2024
Stipulated Date of Completion /
Likely Date of Completion
September 30 2024
Status
19%
Completed
Cost (₹)
Estimated at ₹ 7,252,638.47
Awarded for ₹ 7,816,121.71

Project highlights

Fire-fighting, fire alarm and fire supression system of the building.

 
Gallery Image
Contractors
M/s. Antifire Systems
Gallery Image
Consultants
M/s. KICONS Limited
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of NICU at Goa Medical College, Bambolim at Goa-Supply, Installation, Testing and Commissioning of DG Set.

View Project
Similar Project

Construction of IInd phase of Goa Dental College and Hospital at Bambolim, Goa SH: CCTV, Audio Visual Conferencing, Queue Management and other allied works

View Project
Similar Project

Construction of New Hospital Block in place of existing Hospital for Institute of Psychiatry & Human Behaviour, Goa : Substation and allied works – Electrical

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.