Project Duration
Stipulated Date of Commencement June 26 2023
Stipulated Date of Completion /
Likely Date of Completion
September 30 2024
Status
70%
Completed
Cost (₹)
Estimated at ₹ 5,232,093.87
Awarded for ₹ 4,843,757.08

Project highlights

HVAC works.

 
Gallery Image
Contractors
M/s Shree Manguirish Air Conditioning Co.
Gallery Image
Consultants
M/s. KICONS Limited
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing & Commissioning of Hospital Furniture.

View Project
Similar Project

Supply, Installation, Testing and Commissioning of 100KLD Sewage Treatment Plant and allied Civil works.

View Project
Similar Project

Construction of IInd Phase of Goa Dental College and Hospital at Bambolim, Goa -Supply, Installation, Testing and Commissioning of 33 KV Substation & Light fixture works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.