Project Duration
Stipulated Date of Commencement
October 28 2021
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
95%
Completed
Cost (₹)
Estimated at
₹ 134,712,342.12
Awarded for
₹ 151,930,381.32
Project highlights
Expansion of existing Primary Health Centre, Sanguem by constructing new 44 bedded Hospital.
Contractors
M/s. DHIPL Projects Pvt. Ltd.
Consultants
M/s. KICONS Limited