Project Duration
Stipulated Date of Commencement
September 08 2023
Stipulated Date of Completion /
Likely Date of Completion March 07 2025
Likely Date of Completion March 07 2025
Status
23%
Completed
Cost (₹)
Estimated at
₹ 200,830,721.77
Awarded for
₹ 209,742,867.73
Project highlights
The project is G+2 structure which will be used as 50 bedded Hospital.
Contractors
M/s. Shreejikrupa Buildcon Limited
Consultants
M/s. KICONS Limited
See Similar Projects
Balance HVAC works.
View Project
Setting up of 50 Bedded Integrated AYUSH Hospital at South Goa, T.B. Hospital premises, Margao, Salcete – Goa – Civil, Plumbing, Electrical, Lift, HVAC and Fire Fighting works