Project Duration
Stipulated Date of Commencement
May 01 2019
Stipulated Date of Completion /
Likely Date of Completion December 31 2024
Likely Date of Completion December 31 2024
Status
42%
Completed
Cost (₹)
Estimated at
₹ 189,233,374.21
Awarded for
₹ 191,071,252.35
Project highlights
• There will be Three Lecture halls with capacity of 300 seats each.
• There will be One hall with capacity of 600 seats on third floor
Contractors
M/s. Tirupati Sarjan Limited.
Consultants
M/s. FP Project Management
See Similar Projects
Construction Of Multipurpose Hall Having Badminton Court, Gymnasium, Changing Room and Other Facilities at Socorro Ground. – Mechanical, Electrical, Plumbing scope of work pertaining to Lap Pool, Diving Pool and Baby Pool.
View Project
Demolition and reconstruction of Margao Government Industrial Training Institute and Government Multipurpose Higher Secondary School at Borda, Margao,Goa-Phase I.
View Project
Construction of Hostel at Government College of Arts, Science & Commerce at Khandola – Goa.
View Project