Project Duration
Stipulated Date of Commencement
October 19 2019
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
70%
Completed
Cost (₹)
Estimated at
₹ 66,452,706.33
Awarded for
₹ 80,515,340.35
Project highlights
Upgradation of existing rural medical centre to 12 – Bedded Primary Health Centre
Contractors
M/s. Sunil Enterprises
Consultants
M/s. Datta Kare Associates
See Similar Projects
Balance Fire-fighting works
View Project
Balance electrical and LV works
View Project
Balance HVAC works.
View Project





