Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion March 31 2025
Likely Date of Completion March 31 2025
Status
38%
Completed
Cost (₹)
Estimated at
₹ 780,677,230.00
Awarded for
₹ 767,700,000.00
Project highlights
The project consists of construction of a Cable Stayed Bridge.
Length of Bridge including approaches = 705.00 meters
Length of Bridge portion= 545 meters
Width of Deck(Road surface with footpath) = 12m
— Matter is in Supreme Court. (This can be removed from Chart till the work is resumed.)
Contractors
M/s. M.Venkata Rao Infra Projects Pvt. Ltd
Consultants
M/s. TPF Engineering Pvt. Ltd.