Project Duration
Stipulated Date of Commencement
October 06 2016
Stipulated Date of Completion /
Likely Date of Completion July 15 2024
Likely Date of Completion July 15 2024
Status
95%
Completed
Cost (₹)
Estimated at
₹ 1,088,080,408.00
Awarded for
₹ 1,208,723,650.73
Project highlights
The building is (stilt + 5floors) RCC framed structure with court halls, judges chamber, library for advocates etc.
Contractors
M/s. M.Venkata Rao Infra Projects Pvt. Ltd
Consultants
M/s. Shrikhande Consultants Ltd.
Sub Works
This project involved 3 sub works. The details of the same available below
1
Construction of New District & Session Court Complex at Merces,Tiswadi,Goa – Interior & Furniture Works.
97% completed
Project Duration
Stipulated Date of Commencement
July 22 2023
Stipulated Date of Completion /
Likely Date of Completion July 21 2024
Likely Date of Completion July 21 2024
Status
97%
Completed
Cost (₹)
Estimated at
₹ 351,669,705.00
Awarded for
₹ 325,337,450.83
Project highlights
Interior & Furniture Works for the court building
Contractors
M/s. Godrej and Boyce Mfg. Co. Ltd.
Consultants
M/s. Shrikhande Consultants Ltd.
2
Construction of New District & Sessions Court Complex at Merces, Tiswadi – Goa: Audio Video system.
85% completed
Project Duration
Stipulated Date of Commencement
January 17 2024
Stipulated Date of Completion /
Likely Date of Completion July 15 2024
Likely Date of Completion July 15 2024
Status
85%
Completed
Cost (₹)
Estimated at
₹ 92,544,800.15
Awarded for
₹ 88,438,403.79
Project highlights
Audio Visual system provided in the court Halls, Conference rooms & Multi-purpose Hall.
Contractors
M/s. Shrishti Enterprises
Consultants
M/s. Shrikhande Consultants Ltd.
3
Construction of New District & Sessions Court Complex at Merces, Tiswadi – Goa: Balance Electrical works
10% completed
Project Duration
Stipulated Date of Commencement
June 07 2024
Stipulated Date of Completion /
Likely Date of Completion August 06 2024
Likely Date of Completion August 06 2024
Status
10%
Completed
Cost (₹)
Estimated at
₹ 3,279,407.36
Awarded for
₹ 3,350,000.00
Project highlights
Panels required for additional HVAC requirements from the Court and Façade Lighting.
Contractors
M/s. Volton Engineering (I) Pvt. Ltd.
Consultants
M/s. Shrikhande Consultants Ltd.
See Similar Projects
Construction of Sainik Aramgarh (Rest House) at Bambolim -Furniture works.
View Project
Development of work place at third floor, Goa Van Bhavan, Forest Department, Altinho, Panaji-Goa.
View Project
Construction of Multipurpose Community Hall for Department of Tribal Welfare at Kalmamol Borim in Ponda Taluka -‘Balance Work
View Project