Project Duration
Stipulated Date of Commencement October 29 2021
Stipulated Date of Completion /
Likely Date of Completion
December 31 2024
Status
16%
Completed
Cost (₹)
Estimated at ₹ 24,015,019.00
Awarded for ₹ 26,643,291.78

Project highlights

1. Built-up area:810 sqm.
2. Ground Floor – 5 Shops, Health Centre, Library, Gym House with Changing Rooms, Bank, Panchayat Administration Office & Cabins, Conference Room and Toilets.

 
Gallery Image
Contractors
M/s. Shri Hari Krishna Construction
Gallery Image
Consultants
M/s. Vaishali Pednekar Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Multipurpose Hall with Indoor Games Stadium of VP Nagoa.

View Project
Similar Project

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa .-CCTV works

View Project
Similar Project

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Stage lighting and Drapery works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.