Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
25%
Completed
Cost (₹)
Estimated at
₹ 31,378,334.00
Awarded for
₹ 27,900,000.00
Project highlights
Mechanical, Electrical, Plumbing Scope of Work Pertaining to all pools
Contractors
M/S. Chlorination Engineering
Consultants
M/s.Banaji & Associates