Project Duration
Stipulated Date of Commencement August 24 2023
Stipulated Date of Completion /
Likely Date of Completion
July 27 2024
Status
90%
Completed
Cost (₹)
Estimated at ₹ 21,027,260.00
Awarded for ₹ 18,149,769.44

Project highlights

Interior and furniture including signages murals etc.

 
Gallery Image
Contractors
M/s. Virender Kumar & Co.
Gallery Image
Consultants
M/s. UCJ Architecture & Environment
 
Similar Projects

See Similar Projects

Similar Project

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa.- 11 KV HT Substation Work.

View Project
Similar Project

Construction of Panchayat Ghar and shopping complex, along with Community hall at Bazar shiroda in the property of V.P.Shiroda.

View Project
Similar Project

Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Road and Misc. Works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.