Project Duration
Stipulated Date of Commencement
December 21 2015
Stipulated Date of Completion /
Likely Date of Completion April 20 2016
Likely Date of Completion April 20 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,709,441.00
Awarded for
₹ 11,818,492.26
Project highlights
Ella & Margao: 1. Total area of the premises: 206.00sq.m.
2. Laboratory comprises of Cabin, office, Dark Chemical Storage Room, Main Hall, Preparation/Drying Room, Soil Storage Room, Research Room and Toilets.
3. Vitrified flooring for the cabin & office space and Kotah Flooring for main hall and other storage rooms.
4. Granite counter, soil storage racks and ramp upto soil storage room for the vehicle.
Contractors
M/s. Trivikram Constructions
Consultants
M/s. Creative Abode
See Similar Projects
Panaji to Patradevi (Part II) – Chainage 21.90 km. to 43.80 km.
View Project
Development Plan of the site of Shree Mahalasa Devi Temple at Verna-Phase I – Civil, Plumbing and Electrical work.
View Project
Interior work for branch office of Directorate of Food and Drugs Administration in Old Collectorate building, Margao, Goa
View Project