Status
Completed
Contractors
Consultants
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of building at Patto with provision for Gas Insulated Sub Station, Panaji, Goa Phase I – Electrical Works
100% completed
Project Duration
Stipulated Date of Commencement
December 04 2021
Stipulated Date of Completion /
Likely Date of Completion June 03 2022
Likely Date of Completion June 03 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,212,628.80
Awarded for
₹ 1,249,999.00
Project highlights
Electrification of Gas Insulated Sub Station Building
Contractors
M/s.Volton Engineering India Private Limited
Consultants
M/s. Vijaykumar Sawant & Associates
See Similar Projects
Construction of Yojana Bhavan for Directorate of Planning, Statistics and Evaluation at Porvorim, Goa -Civil, plumbing, electrical, elevators, HVAC, fire fighting and landscaping works
View Project
Construction of Yojana Bhavan for Directorate of Planning, Statistics & Evaluation at Porvorim, Goa – Additional works
View Project
Supply & Installation of Compactors in Record Room of Survey Department and Sub Civil Registrar.
View Project