Project Duration
Stipulated Date of Commencement
May 20 2016
Stipulated Date of Completion /
Likely Date of Completion August 19 2016
Likely Date of Completion August 19 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 92,54,873.00
Awarded for
₹ 83,28,150.00
Project highlights
The scope of work includes beautification of Shree Navadurga Temple premises by laying interlocking paver blocks.
Contractors
M/s. Deshpande Constructions
Consultants
M/s. UCJ Architecture & Environment