Project Duration
Stipulated Date of Commencement
February 16 2015
Stipulated Date of Completion /
Likely Date of Completion March 02 2015
Likely Date of Completion March 02 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,698,000.00
Awarded for
₹ 1,739,000.00
Project highlights
Supply of fabricated custumized toe cranes
Contractors
M/s. Chowgule Industries (I) Ltd.
Consultants
In-house (GSIDC)