Project Duration
Stipulated Date of Commencement
April 21 2004
Stipulated Date of Completion /
Likely Date of Completion November 08 2004
Likely Date of Completion November 08 2004
Status
100%
Completed
Cost (₹)
Awarded for
₹ 186,500,000.00
Project highlights
The Multiplex is situated on the Government Land near the Panjim Municipal Market, the seating Capacity of the Multiplex is 1272 seats spread over 4 Auditoriums.
Contractors
M/s. Inox Leisures Ltd.
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD