Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion March 26 2014
Likely Date of Completion March 26 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 499,870.00
Awarded for
₹ 551,185.00
Project highlights
Electrical Works
Contractors
M/s.Desai Electrical & Electronics Sales & Services
Consultants
In-house (GSIDC)