Project Duration
Stipulated Date of Commencement
July 15 2013
Stipulated Date of Completion /
Likely Date of Completion September 14 2013
Likely Date of Completion September 14 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,032,679.00
Awarded for
₹ 21,299,865.00
Contractors
M/s. Trivikram Constructions
Consultants
Oracle Structural Consultants
Sub Works
This project involved 2 sub works. The details of the same available below
1
Construction of two number of sheds for treatment of dry waste within the Corporation of the City of Panaji (CCP) jurisdiction – Electrical works at St. Inez.
100% completed
Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion March 26 2014
Likely Date of Completion March 26 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 499,870.00
Awarded for
₹ 551,185.00
Project highlights
Electrical Works
Contractors
M/s.Desai Electrical & Electronics Sales & Services
Consultants
In-house (GSIDC)
2
Construction Of Two Numbers Of Sheds For Treatment Of Dry Waste Within The Corporation Of City Of Panaji (Ccp) Jurisdiction -Electrical Works At Patto
100% completed
Project Duration
Stipulated Date of Commencement
May 16 2014
Stipulated Date of Completion /
Likely Date of Completion June 15 2014
Likely Date of Completion June 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 445,576.00
Awarded for
₹ 521,000.00
Project highlights
Electrical Works
Contractors
M/s.Desai Electrical & Electronics Sales & Services
Consultants
In-house (GSIDC)
See Similar Projects
Supply of hydraulic wrecker crane with under lift capacity of 2.5 tons.
View Project
Panaji to Patradevi (Part II) – Chainage 21.90 km. to 43.80 km.
View Project
Improvement of Shree Navadurga Temple premises by laying interlocking paver blocks at Deulwada, Pale in V.P. Pale Cottombi in Sankhali Constituency
View Project