Project Duration
Stipulated Date of Commencement
September 01 2015
Stipulated Date of Completion /
Likely Date of Completion September 30 2015
Likely Date of Completion September 30 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 482,628.00
Awarded for
₹ 446,140.00
Project highlights
Providing 11 KV transformer substation for releasing of electrical power supply to Commercial Tax Office,Vasco.
Contractors
M/s. Karant Electricals
Consultants
M/s. Saolapurkar and Associates