Project Duration
Stipulated Date of Commencement
April 21 2018
Stipulated Date of Completion /
Likely Date of Completion May 20 2018
Likely Date of Completion May 20 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,968,800.00
Awarded for
₹ 2,701,502.43
Project highlights
Providing roofing on terrace of Block A of EDC House to prevent water leakages and to protect the interior work of GSIDC office at 7th & 8th floor.
Contractors
M/s.Vishal Engineering, Kolhapur
Consultants
M/s.Intrinsic Classic