Project Duration
Stipulated Date of Commencement
September 10 2014
Stipulated Date of Completion /
Likely Date of Completion August 01 2015
Likely Date of Completion August 01 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,882,348.32
Awarded for
₹ 3,805,873.00
Project highlights
work consists of providing fire suppression system for UPS and server room.
Contractors
M/s.Douse Fire System Pvt. Ltd.,
Consultants
M/s. KICONS Ltd.,