Project Duration
Stipulated Date of Commencement
December 19 2014
Stipulated Date of Completion /
Likely Date of Completion March 18 2015
Likely Date of Completion March 18 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,481,698.00
Awarded for
₹ 39,884,083.00
Project highlights
Interior Works for IT Hub
Contractors
M/s. Srishti Enterprises
Consultants
M/s. KICONS Ltd.,