Project Duration
Stipulated Date of Commencement March 26 2007
Stipulated Date of Completion /
Likely Date of Completion
July 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,534,853.00
Awarded for ₹ 2,484,551.20
 
Gallery Image
Contractors
M/s. A Square Techno Solution
Gallery Image
Consultants
M/s. Effective Architectural Services
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Audio, Video and CCTV Surveillance System for District Library at Navelim, Margao.

View Project
Similar Project

Renovation of Childrens Park at Sankhali Housing Board

View Project
Similar Project

Balance beautification works from Miramar Circle to Betim Ferry Ramp

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.