Project Duration
Stipulated Date of Commencement
January 02 2020
Stipulated Date of Completion /
Likely Date of Completion April 15 2020
Likely Date of Completion April 15 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,311,387.44
Awarded for
₹ 1,590,670.00
Contractors
M/s.Techser Power Solutions (P) Ltd
Consultants
M/s. Effective Architectural Services