Project Duration
Stipulated Date of Commencement
March 03 2014
Stipulated Date of Completion /
Likely Date of Completion July 02 2015
Likely Date of Completion July 02 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,44,66,205.12
Awarded for
₹ 78,429,459.65
Contractors
M/s.Srishti Enterprises
Consultants
M/s. Effective Architectural Services
See Similar Projects
Phase I : Land Development
View Project
Carpentry work.
View Project
Digital Multifunctional Copiers
View Project





