Project Duration
Stipulated Date of Commencement
December 17 2012
Stipulated Date of Completion /
Likely Date of Completion April 16 2013
Likely Date of Completion April 16 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 31,641,360.00
Awarded for
₹ 31,593,913.87
Contractors
M/s. T. S. Mistry
Consultants
M/s. Effective Architectural Services
See Similar Projects
Construction of two number of sheds for treatment of dry waste within the Corporation of the City of Panaji (CCP) jurisdiction – Electrical works at St. Inez.