Project Duration
Stipulated Date of Commencement
April 02 2011
Stipulated Date of Completion /
Likely Date of Completion October 02 2011
Likely Date of Completion October 02 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,636,345.00
Awarded for
₹ 22,999,999.00
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. Effective Architectural Services