Project Duration
Stipulated Date of Commencement
January 20 2011
Stipulated Date of Completion /
Likely Date of Completion July 19 2011
Likely Date of Completion July 19 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,548,704.00
Awarded for
₹ 11,883,785.00
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd..
Consultants
M/s. Effective Architectural Services