Project Duration
Stipulated Date of Commencement November 27 2010
Stipulated Date of Completion /
Likely Date of Completion
June 26 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,59,76,814.81
Awarded for ₹ 3,25,13,771.00
 
Gallery Image
Contractors
M/s. Rohini Industrial Electricals Ltd.
Gallery Image
Consultants
M/s. Effective Architectural Services
 