Project Duration
Stipulated Date of Commencement
July 26 2018
Stipulated Date of Completion /
Likely Date of Completion March 25 2019
Likely Date of Completion March 25 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 35,100,310.00
Awarded for
₹ 31,895,244.00
Project highlights
Interior works for Sanjay School building at Vasco & Porvorim which includes new modular furnitures for special childrens, carpentary works, new stage along with acoustics etc.
Contractors
M/s. Macro Enterprises
Consultants
M/s Rajesh Kenkre
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Ponda Taluka: GPS Volvoi & GPS Veling
View Project
Upgradation/Renovation of Government College at Quepem, Goa -Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.
View Project
Repairs/Upgradation & maintenance of Government Schools in State of Goa – Civil, Plumbing & Electrical works – Package D – Quepem Taluka (GPS Katta Fatorpa, GPS Shirlim)
View Project