Project Duration
Stipulated Date of Commencement November 13 2019
Stipulated Date of Completion /
Likely Date of Completion
December 12 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,832,868.00
Awarded for ₹ 3,340,300.00
 
Gallery Image
Contractors
M/s. Pro Imaging Technologies
Gallery Image
Consultants
M/s. UCJ Architecture & Environment
 
Similar Projects

See Similar Projects

Similar Project

Computer work.

View Project
Similar Project

Construction of Forest Headquarters Building at Altinho Old IPHB Complex -Interior & Furniture works.

View Project
Similar Project

Construction of new building for SCERT at Porvorim, Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.