Project Duration
Stipulated Date of Commencement
January 23 2019
Stipulated Date of Completion /
Likely Date of Completion April 22 2019
Likely Date of Completion April 22 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 26,885,072.00
Awarded for
₹ 19,212,281.50
Project highlights
Projects involves providing interior furniture and readaymade furniture
Contractors
M/s. T. S. Mistry,
Consultants
M/s. UCJ Architecture & Environment