Project Duration
Stipulated Date of Commencement
October 12 2013
Stipulated Date of Completion /
Likely Date of Completion December 11 2013
Likely Date of Completion December 11 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,321,131.00
Awarded for
₹ 2,375,201.00
Project highlights
Compactors in Record rooms
Contractors
M/s. Kompress (India) Pvt. Ltd.
Consultants
In-house (GSIDC)