Project Duration
Stipulated Date of Commencement
January 31 2013
Stipulated Date of Completion /
Likely Date of Completion April 30 2013
Likely Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,228,580.00
Awarded for
₹ 16,956,091.00
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.