Project Duration
Stipulated Date of Commencement
January 27 2013
Stipulated Date of Completion /
Likely Date of Completion February 25 2013
Likely Date of Completion February 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,59,583.00
Awarded for
₹ 4,023,779.00
Project highlights
Signages works
Contractors
M/s. Harshada Trading Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.