Project Duration
Stipulated Date of Commencement February 16 2010
Stipulated Date of Completion /
Likely Date of Completion
August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,33,96,780.00
Awarded for ₹ 21,149,474.00
 
Gallery Image
Contractors
M/s. Imperial Engineering Co.
Gallery Image
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of 315 KVA transformer.

View Project
Similar Project

Raising the Existing Compound Wall and Providing Additional Gutters

View Project
Similar Project

False ceiling, interior, furniture, signage, security installation and other miscellaneous works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.