Project Duration
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
Completed
Contractors
Consultants
Sub Works
This project involved 20 sub works. The details of the same available below
1
Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa -Civil, Plumbing, Internal Electrical & Fire Fighting works
100% completed
Project Duration
Stipulated Date of Commencement
December 21 2007
Stipulated Date of Completion /
Likely Date of Completion June 20 2010
Likely Date of Completion June 20 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 573,453,985.00
Awarded for
₹ 734,634,449.00
Project highlights
Basement + Ground + 5 RCC framed structure
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
2
Lift work
100% completed
Project Duration
Stipulated Date of Commencement
February 16 2010
Stipulated Date of Completion /
Likely Date of Completion August 15 2010
Likely Date of Completion August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,729,540.00
Awarded for
₹ 27,700,000.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
3
External Electrical works.
100% completed
Project Duration
Stipulated Date of Commencement
February 16 2010
Stipulated Date of Completion /
Likely Date of Completion August 15 2010
Likely Date of Completion August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,33,96,780.00
Awarded for
₹ 21,149,474.00
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
4
Air conditioning works.
100% completed
Project Duration
Stipulated Date of Commencement
June 16 2011
Stipulated Date of Completion /
Likely Date of Completion November 15 2011
Likely Date of Completion November 15 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,57,17,757.00
Awarded for
₹ 23,604,023.00
Contractors
M/s. Manguirish Air Conditioning Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
5
Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)
100% completed
Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion January 14 2012
Likely Date of Completion January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,27,37,030.00
Awarded for
₹ 9,146,323.00
Contractors
M/s. Eagle Construction Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
6
Audio Visual Equipments for conference system and AV room
100% completed
Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion January 14 2012
Likely Date of Completion January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,34,15,719.00
Awarded for
₹ 13,448,394.00
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
7
Telephone Exchange and UPS (Part A- UPS work)
100% completed
Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion January 14 2012
Likely Date of Completion January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 44,92,891.00
Awarded for
₹ 4,693,205.00
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
8
Telephone Exchange and UPS (Part B – IP Telephony and Video Conferencing work)
100% completed
Project Duration
Stipulated Date of Commencement
February 01 2012
Stipulated Date of Completion /
Likely Date of Completion March 16 2012
Likely Date of Completion March 16 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,00,26,362.00
Awarded for
₹ 5,637,190.00
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
9
Decorative Glazing for staircase blocks.
100% completed
Project Duration
Stipulated Date of Commencement
April 22 2012
Stipulated Date of Completion /
Likely Date of Completion May 07 2012
Likely Date of Completion May 07 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 87,89,272.80
Awarded for
₹ 8,250,144.00
Project highlights
Decorative Glazing works
Contractors
M/s. R. S. Lawande
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
10
Carpentry and interior work.
100% completed
Project Duration
Stipulated Date of Commencement
April 22 2012
Stipulated Date of Completion /
Likely Date of Completion August 21 2012
Likely Date of Completion August 21 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,96,84,461.30
Awarded for
₹ 53,022,057.00
Project highlights
Carpentry works
Contractors
M/s.Concept Creator
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
11
Readymade furniture works
100% completed
Project Duration
Stipulated Date of Commencement
July 09 2012
Stipulated Date of Completion /
Likely Date of Completion June 12 2012
Likely Date of Completion June 12 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,28,94,732.00
Awarded for
₹ 37,798,417.00
Project highlights
Readymade Furniture works
Contractors
M/s. Durian Industries Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
12
Internal, external and special lighting fixtures (Part B : External lights and façade lighting)
100% completed
Project Duration
Stipulated Date of Commencement
August 11 2012
Stipulated Date of Completion /
Likely Date of Completion December 23 2012
Likely Date of Completion December 23 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,09,68,986.00
Awarded for
₹ 6,849,960.00
Contractors
M/s. Shanti Electrical Enterprises Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
13
Supply of trees, grass, grass covers & allied material for landscaping works.
100% completed
Project Duration
Stipulated Date of Commencement
January 17 2013
Stipulated Date of Completion /
Likely Date of Completion February 15 2013
Likely Date of Completion February 15 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,02,563.00
Awarded for
₹ 2,983,810.00
Project highlights
Landscaping works
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
14
Signages work
100% completed
Project Duration
Stipulated Date of Commencement
January 27 2013
Stipulated Date of Completion /
Likely Date of Completion February 25 2013
Likely Date of Completion February 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,59,583.00
Awarded for
₹ 4,023,779.00
Project highlights
Signages works
Contractors
M/s. Harshada Trading Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
15
Supply, installation, testing and commissioning of Precision AC, UPS, D. G. Set, Transformer, and related electrical works
100% completed
Project Duration
Stipulated Date of Commencement
January 31 2013
Stipulated Date of Completion /
Likely Date of Completion April 30 2013
Likely Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,228,580.00
Awarded for
₹ 16,956,091.00
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
16
CPOE switches
100% completed
Project Duration
Stipulated Date of Commencement
April 12 2012
Stipulated Date of Completion /
Likely Date of Completion October 01 2013
Likely Date of Completion October 01 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ ----
Awarded for
₹ 1,539,900.00
Contractors
M/s. AGC Networks Limited
Consultants
In-house (GSIDC)
17
Supply & Installation of Compactors in Record Room of Survey Department and Sub Civil Registrar.
100% completed
Project Duration
Stipulated Date of Commencement
October 12 2013
Stipulated Date of Completion /
Likely Date of Completion December 11 2013
Likely Date of Completion December 11 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,321,131.00
Awarded for
₹ 2,375,201.00
Project highlights
Compactors in Record rooms
Contractors
M/s. Kompress (India) Pvt. Ltd.
Consultants
In-house (GSIDC)
18
Raising the Existing Compound Wall and Providing Additional Gutters
100% completed
Project Duration
Stipulated Date of Commencement
October 16 2013
Stipulated Date of Completion /
Likely Date of Completion February 15 2014
Likely Date of Completion February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,002,100.00
Awarded for
₹ 4,991,914.50
Project highlights
Additional gutters & Compound wall works
Contractors
M/s. A. Ponnuraj
Consultants
In-house (GSIDC)
19
– Additional Miscellaneous work.
100% completed
Project Duration
Stipulated Date of Commencement
January 23 2015
Stipulated Date of Completion /
Likely Date of Completion May 22 2015
Likely Date of Completion May 22 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,853,393.00
Awarded for
₹ 13,328,661.00
Project highlights
Additional furniture & minor civil works.
Contractors
M/s. Concept Creators
Consultants
M/s. Nitin Arolkar
20
Supply, installation, testing & commissioning of C1287 RMU
100% completed
Project Duration
Stipulated Date of Commencement
April 23 2018
Stipulated Date of Completion /
Likely Date of Completion June 22 2018
Likely Date of Completion June 22 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,690,000.00
Awarded for
₹ 2,645,220.00
Contractors
M/s. Pristine Engineering Services
Consultants
In-house (GSIDC)
See Similar Projects
Supply of Adult folding wheel chair for pilgrims for Exposition 2014 at Old Goa.
View Project
Construction of Forest Headquarters Building at Altinho Old IPHB Complex
View Project
Supply, Installation, Testing & Commissioning of CCTV system at Goa Medical College.
View Project